Construction RFI form and tracking log
Excel / Google Sheets compatible · printable form sheet · no sign-up required
A one-question RFI form you can print or send, and a log that shows what you have asked, who owes you an answer and how long it has been sitting. The filled example runs a real-shaped question, a beam bearing on a wall thinner than the drawing shows, from the site to the answer and the revised detail. The preview below is that example.
Template and page last reviewed November 4, 2026.
What is in the file
| Field | Entry |
|---|---|
| Sent to | M. Chen, project architect |
| Issued, and response needed by | 18 Aug 2026, by 22 Aug 2026 |
| Drawing reference | A-203 rev C, detail 4; spec section 06 10 00 |
| Question | Drawing A-203 rev C shows the beam pocket at grid C/2 bearing on the existing foundation wall, but the wall is 190mm block, not the 240mm shown. What bearing detail should be used? |
| Proposed interpretation | Proposed: pour a 400 x 400 x 200mm concrete pad on the block, doweled into the wall, and bear the beam on that. Please confirm or issue an alternative detail. |
| Impact while waiting | Schedule: framing at grid C on hold, about 2 days. Cost: not yet priced - a pad pour is a small extra if the detail is accepted. |
| Response | Use the pad as proposed, 400 x 400 x 200mm, 20 MPa, two 15M dowels epoxied 150mm into the block. Revised detail issued as A-203 rev D. |
| RFI | Subject | Sent to | Issued | Due | Answered | Days open |
|---|---|---|---|---|---|---|
| RFI-001 | Window head height, front elevation | M. Chen | 28 Jul 2026 | 1 Aug 2026 | 31 Jul 2026 | 3 |
| RFI-002 | Kitchen island outlet locations | Owner | 4 Aug 2026 | 8 Aug 2026 | 11 Aug 2026 | 7 |
| RFI-003 | Stair headroom at basement landing | M. Chen | 12 Aug 2026 | 15 Aug 2026 | Still open | 17 |
| RFI-004 | Beam bearing at grid C/2 | M. Chen | 18 Aug 2026 | 22 Aug 2026 | 21 Aug 2026 | 3 |
Four steps to a working document
One question per RFI
An RFI asking three things comes back answering one. Split them, even when it feels like more paperwork: it is less than chasing two unanswered halves.
Cite the drawing and its revision
"A-203 rev C, detail 4" is checkable a year later. "The plans show" is not, and it is the difference between a decision you can point at and a conversation nobody remembers.
Say what you think the answer is
A proposed interpretation turns a problem the designer has to solve into one they only have to confirm. It is often the quickest way to get an answer back.
Log it the day you send it
Not the day it comes back. The log's days-open column counts to the answer, or to today while it is still open, which is the number worth showing at a site meeting.
An answer to an RFI is not by itself approval of extra cost or time. If the response changes the scope, raise a change order under your contract: clarification and variation are different things, and treating one as the other is how work gets done unpaid.
When the spreadsheet stops scaling
BuildersBridge does not include an RFI or submittal workflow. What it does do is keep the completed forms filed against the job with the drawings and permits, so the answer is findable when someone asks in two years.
See how it works in BuildersBridgeCommon questions
What is an RFI in construction?
A request for information: a formal written question to the designer or owner when the drawings, specification or site conditions do not answer something you need to build. It is a record as much as a question, because the response becomes part of what was agreed.
What should an RFI include?
The project and RFI number, who is asking and who must answer, the date sent and the date a response is needed, the drawing or specification reference with its revision, one clear question, your proposed interpretation if you have one, and the cost or schedule impact of waiting.
How is an RFI different from a submittal or a change order?
An RFI asks what was intended. A submittal proposes a specific product or method for approval before it is used. A change order records an agreed change to price or time. An RFI answer can lead to a change order, but it is not one, and neither is a submittal approval.
Does BuildersBridge have an RFI workflow?
No. There is no RFI or submittal module in the product today, which is why this is a standalone template rather than a feature page. Document storage against the job is there, so completed forms live with the drawings they relate to.
How long should I give for a response?
Your contract usually sets it. Put the date on the form rather than leaving it open, and record the date the answer actually arrives. In the example, RFI-002 was answered three days after its due date; the gap between those two dates is the number to raise if it becomes a pattern.