What has to be true before you send the final invoice and hand over the keys: every permit and test on file, every change billed, the warranties and manuals collected, the records kept, the open items named, and a register of everything you gave the owner, with dates. The filled example is the fictional ensuite job from our other templates on the day of its final invoice, with three items still open. The preview below is that example.

Download the closeout checklist (.xlsx)

Excel / Google Sheets compatible · checklist, handover register and filled examples · no sign-up required

Template and page last reviewed November 4, 2026.

What is in the file

Filled example: Example: ensuite renovation, Edmonton AB (fictional) at handoverThe example checklist and handover register in the download, read on 31 May 2027, the date of the final invoice. The blank checklist starts with 17 standard items under the same six headings, and room for your own.
Closeout checklist
SectionItemEvidenceResponsibleStatusDate
Permits and inspectionsPermit closed, if one was taken outFinal inspection record from the permit holderClient (permit by owner, per the scope)Outstanding
Permits and inspectionsShower waterproofing flood testQC checklist sign-off, photo 2027-03-25-flood-test-24h.jpgD. Kaur, site leadDone25 Mar 2027
Permits and inspectionsEvery tap, drain and flush run and checked for leaksFinal walk note in the daily logPlumbing subDone28 May 2027
Permits and inspectionsElectrical permitElectrical work is excluded from the scopeNot applicable
Changes and moneyEvery change order signed and billedCO-001 signed 2027-03-22; billed on INV-1003ContractorDone31 May 2027
Changes and moneyFixture allowance reconciled against what was boughtPO-203, inside the $2,800 allowanceContractorDone31 May 2027
Changes and moneyFinal invoice issued, with holdback shown as retainedINV-1003ContractorDone31 May 2027
Warranties and manualsContractor's workmanship warranty, in writingWarranty letter, on the terms in your contractContractorDone31 May 2027
Warranties and manualsManufacturer manuals and warranties: vanity, toilet, faucets, glass doorPDFs and the paper copiesFixture and glass suppliersOutstanding
RecordsTile, grout and membrane product names and lot numbers recordedHandover registerContractorDone31 May 2027
RecordsPhotos of the open walls and substrate kept with the job2027-03-15-shower-open-to-studs.jpg, 2027-03-15-bottom-plate-dry.jpgD. Kaur, site leadDone15 Mar 2027
RecordsPaint colours and sheens recordedHandover registerContractorDone31 May 2027
Outstanding itemsDeficiency list signed, or every open item dated and assignedDeficiency list from the final walkContractorOutstanding
HandoverSpare materials left with the ownerOne box of tile and a part bag of groutContractorDone31 May 2027
HandoverOwner walk-through: shut-off valves, grout and glass careDaily log entryD. Kaur, site leadDone28 May 2027
HandoverSite protection removed, lockbox returnedD. Kaur, site leadDone31 May 2027
Handover register
Document or itemWhat it coversGiven toDate
Workmanship warranty letterThe contractor's warranty on the ensuite workClient31 May 2027
Fixture manuals and warrantiesVanity, toilet and faucetsClient31 May 2027
Glass door care and warranty sheetFrameless shower door (CO-001)Not yet
Product recordTile, grout, membrane and paint: product, colour and lot numberClient31 May 2027
Waterproofing recordFlood test sign-off and the photos before tileClient31 May 2027
Change order and final invoiceCO-001 and INV-1003Client31 May 2027
Spare materialsOne box of tile, part bag of groutClient31 May 2027
Where the job stands
ItemCount
Checklist items done12
Outstanding, each with a name against it3
Not applicable to this job1
Documents handed over / still to give6 / 1
Holdback still retained across the three invoices (not a checklist item)$1,255.03
Not on the checklist, on purpose
ItemWhy
Substantial performance or completionA legal milestone set by your contract and your province's or state's legislation, often certified by the owner's consultant. A finished checklist does not establish it.
Holdback or retainage releaseReleased when the contract and the legislation allow, usually after a period with no lien registered. The checklist records that holdback was shown as retained, not that it is due.
The lien periodStarts from a date the legislation defines, which may not be the day you hand over the keys. Check the rule where the job is.

Download the closeout checklist (.xlsx)

How to use it

Four steps to a working document

1

Start before the last week

Warranties, manuals and inspection records take the longest to collect. Open the checklist when the job is about 90% done, not on the day of the final walk.

2

Done means it is in the file

Mark a row Done only when the evidence is in the job file, and say where. "The plumber said it passed" is Outstanding.

3

Put a name on everything open

Every Outstanding row gets a person and, in the notes, a date. A list of open items without names is a list of things nobody will do.

4

Get the register acknowledged

Hand over documents and spare materials against the register and have the owner initial each line. It is the record of what they received, and when.

Finishing this checklist is not substantial performance, completion or a holdback release. Those are legal milestones set by your contract and the legislation where the job is, and the lien period may run from a different date than the day you hand over the keys. Check each one before you rely on it. This is not legal advice.

When the spreadsheet stops scaling

In BuildersBridge, a job that is 90% done or marked complete shows a closeout card to the people who can see its financials: open tasks, change orders still waiting on the client, contract left to bill, holdback still retained, money owed, whether any documents are shared with the client, and whether the job is marked complete. This checklist covers the paperwork that card does not: permits, test records, warranties and the handover register.

See how it works in BuildersBridge
FAQ

Common questions

What goes in a construction closeout checklist?

Permits and inspection records, your own test records, change orders and allowances settled, the final invoice, the contractor's and manufacturers' warranties and manuals, records such as product lot numbers and photos of concealed work, the open deficiency items, and the owner handover itself.

How is it different from a punch list?

A punch list, or deficiency list, is the work still to put right. The closeout checklist is everything else that has to be finished and filed for the job to be over, and the deficiency list is one row on it.

Does a completed checklist mean holdback can be released?

No. Holdback or retainage is released when your contract and the legislation allow, usually after a period with no lien registered. In the example, $1,255.03 is still retained across three invoices on the day the checklist is worked, and that is correct.

What is a handover register?

A list of every document and item you gave the owner, with the date and an acknowledgement: warranty letters, manuals, product records, test records, spare materials. When a warranty question comes up in three years, it is the page that settles what they were given.

Does BuildersBridge have a closeout feature?

Partly. A job that is 90% done or marked complete shows a closeout card with seven steps worked out from the job's own records, visible to people who can see the job's financials. Permits, test records, warranties and the handover register are not on it, which is what this template is for. Documents you share with the client appear in their portal.

Can I use it in Google Sheets?

Yes. Upload the .xlsx to Google Drive and open it with Sheets. The status dropdowns and the counts carry over.